v*****z 发帖数: 3067 | 1 almost 90% done.
in progress inspection pass!!
better than those contractor work.
good enough to pass.
next week will get final inspection. |
v*****z 发帖数: 3067 | 2
【在 v*****z 的大作中提到】 : almost 90% done. : in progress inspection pass!! : better than those contractor work. : good enough to pass. : next week will get final inspection.
|
e*****3 发帖数: 610 | 3 崇拜啊。
请教一个问题。
图中ROOF VALLEY里的FLASHING没换掉,BUILDING CODE允许吗?
另外ROOF VALLEY里有的房子用的是FLASHING,有的直接用的SHINGLE (我猜大该是
折一个角度),有啥区别?
【在 v*****z 的大作中提到】
|
q**j 发帖数: 10612 | |
c******n 发帖数: 4965 | 5 do u need to hire some helpers to do this?
【在 v*****z 的大作中提到】 : almost 90% done. : in progress inspection pass!! : better than those contractor work. : good enough to pass. : next week will get final inspection.
|
v*****z 发帖数: 3067 | 6 when the inspector as me the samething.
I told him I want to keep that old one. he say ok.
I just need to paint that into color.
Just buy the flashing in Low's or HD.
you can not used shingle in valley area anymore in sunnyvale.
【在 e*****3 的大作中提到】 : 崇拜啊。 : 请教一个问题。 : 图中ROOF VALLEY里的FLASHING没换掉,BUILDING CODE允许吗? : 另外ROOF VALLEY里有的房子用的是FLASHING,有的直接用的SHINGLE (我猜大该是 : 折一个角度),有啥区别?
|
v*****z 发帖数: 3067 | 7 I did that all by myself.
since I don't want to see anybody fall down from the roof.
【在 c******n 的大作中提到】 : do u need to hire some helpers to do this?
|
c******n 发帖数: 4965 | 8 how much did you save by DIY instead of having contractors do it?
if DIY, is it possible to do tiles instead? anyway material cost is low
【在 v*****z 的大作中提到】 : I did that all by myself. : since I don't want to see anybody fall down from the roof.
|
v*****z 发帖数: 3067 | 9 around 12k or more depend on what you are going to add later, some feature such as dome
in the garage and skylight.
I will do it later. |
x**1 发帖数: 892 | 10 今天看了个房子 屋顶可能有点漏 要换
agent说用什么最便宜的油毛毡 全部加人工要1w多。能给介绍介绍大概有几种材料,人
工各是多少吗? |
|
|
v*****z 发帖数: 3067 | 11 1w多?
he charge you for the entire roofing replacement.
never used a cheapest material for roof.
I only spend 4k for all material.
my roof cost 15k for contractor to do the job.
we got into the detail with them.
I figure out they try to short on everything.
So I do some HW and DIY.
Actually, it is not that difficult.just need a strong arm
material I used.
88 pieces 7/16 OSB board
20 rolls of 30 pound black paper.
110 bundles of 40 yrs shingles
All from HD. |
S******y 发帖数: 1123 | 12 太能干了!
请问采取了什么安全措施? 是否要腰上绑绳子?
谢谢!
(可能今年夏天也要换房顶) |
v*****z 发帖数: 3067 | 13 I don't use any 安全措施. my roof is 2:14 slope(every 14 inch and 2 inch
high)
it is better to have couple people to help.if in sunnyvale area, I may give
you a hand.
I have some tools you can borrow. (you can save few dollars)
later I will post some major tools for roofing. |
f*******s 发帖数: 3046 | 14 这么能干的都要介绍一下背景,不然人人都以为可以DIY,其实不是那么回事:)
give
【在 v*****z 的大作中提到】 : I don't use any 安全措施. my roof is 2:14 slope(every 14 inch and 2 inch : high) : it is better to have couple people to help.if in sunnyvale area, I may give : you a hand. : I have some tools you can borrow. (you can save few dollars) : later I will post some major tools for roofing.
|
v*****z 发帖数: 3067 | 15 My 背景 is little different than anybody.
you are right, not everybody can DIY.
I think you are pretty 能干 too.
【在 f*******s 的大作中提到】 : 这么能干的都要介绍一下背景,不然人人都以为可以DIY,其实不是那么回事:) : : give
|
A**n 发帖数: 54 | 16 你Gutter and down spouse也自己装吗?这个不好弄吧? |
v*****z 发帖数: 3067 | 17 I keep the old one.
【在 A**n 的大作中提到】 : 你Gutter and down spouse也自己装吗?这个不好弄吧?
|
e*****3 发帖数: 610 | 18 rise 2 inches for every 14 inches?
我听说SHINGLE的MINIMUM SLOPE是3/12,一般都是4/12或者5/12的。而且3/12的SLOPE
UNDERLAYMENT要求不一样,一般要放双层或者用ADHESIVE的加一般的UNDERLAYMENT。
你的ROOF可以用SHINGLE吗?
好象低于3/12的厂家的WARRANTY就自动VOID。
give
【在 v*****z 的大作中提到】 : I don't use any 安全措施. my roof is 2:14 slope(every 14 inch and 2 inch : high) : it is better to have couple people to help.if in sunnyvale area, I may give : you a hand. : I have some tools you can borrow. (you can save few dollars) : later I will post some major tools for roofing.
|
b***p 发帖数: 1398 | 19 nice work, you can start your side business for sure. |
v*****z 发帖数: 3067 | 20 I mean 4:12.
it is on the city roofing code.
every house have different slop. for regular low slop (2:12c or 4:12)
you have to check on your city code.
I went to the city ask the inspector 3 time of the code which I'm not sure.
My roof already pass the in progress inspection. that is a 40 years shingle.
SLOPE
【在 e*****3 的大作中提到】 : rise 2 inches for every 14 inches? : 我听说SHINGLE的MINIMUM SLOPE是3/12,一般都是4/12或者5/12的。而且3/12的SLOPE : UNDERLAYMENT要求不一样,一般要放双层或者用ADHESIVE的加一般的UNDERLAYMENT。 : 你的ROOF可以用SHINGLE吗? : 好象低于3/12的厂家的WARRANTY就自动VOID。 : : give
|
k******h 发帖数: 573 | 21 崇拜一下屋顶 DIY的, 这个slope 说得不专业,第二个数字永远都是12.
give
【在 v*****z 的大作中提到】 : I don't use any 安全措施. my roof is 2:14 slope(every 14 inch and 2 inch : high) : it is better to have couple people to help.if in sunnyvale area, I may give : you a hand. : I have some tools you can borrow. (you can save few dollars) : later I will post some major tools for roofing.
|
v*****z 发帖数: 3067 | 22 final part will be post on monday, which will include major tools for the
project. |